HOL A DELEJ?

What's happening in Hungary's power grid right now?

So where’s the gas? (HU)
50.000Hz frequency: the grid's heartbeat · should stay near 50 Hz
--:--:--
Hover over a country or over Paks
Arrow pointing inward: import
Arrow pointing outward: export
National consumption
0MW
in 30 min
Domestic generation
0MW
in 30 min
Cross-border balance
0MW
in 30 min
Solar share of generation
0%
in 30 min
Paks now
0MW
in 30 min
of domestic generation
imports
What does electricity cost?
Day-ahead price now
€/MWh
This is the wholesale exchange price — not the rate on a household electricity bill.
Cost of imports
per hour
Current imports multiplied by the exchange price: what a full hour would cost at this level.
Since midnight today
Electricity imported since midnight valued at exchange prices, less export revenue.
Today's day-ahead price
Electricity is sold a day ahead: the dashed section has not happened yet, but its exchange price was settled yesterday.
What does that actually mean? · of imports
this many times more than every household in Hungary combined, on average
this far in an electric car on one hour of imported electricity
this many electric kettles switched on at once (2 kW)

When should you use electricity?
Price now
c/kWh
00061218
below the daily middle — worth it around the daily middle above the daily middle — avoid tap or hover an hour
Worth shifting these into the good hours
washing machinedishwashertumble dryer charging an electric carwater heaterpre-cooling with the A/C

Is it raining in the Danube catchment? · 7 nap0mm in the basin today
Today
Over the coming days
Selected day
Heaviest rainfall
The rainfall is a modelled forecast, not a measurement. The blue glow indicates timing only — when rain falling on the catchment could reach Paks — not volume: most of it evaporates or soaks in before ever reaching the Danube.

Paks · up close

The river did not run dry. The cooling-water intakes sit at a fixed height — once the Danube drops below them, the pumps cannot lift water. On top of that, the law caps the temperature of the water returned: 500 m downstream of the outflow channel the Danube may not exceed 30 °C. Together these two limits forced the plant back.

Danube level
0cm
0 m a.s.l. ·
Paks now
0MW
0 MW five days ago
Water temp.
0°C
below the 30 °C limit
Discharge
0m³/s
The plant and the cooling-water path · schematic
Cross-section of the Danube at Paks
How much cooling water is needed?
Now
m³/s
At full load
100m³/s
Plant fully shut down
2.5m³/s

The plant's design basis assumed the 100-year minimum was more than 1 m higher than the 2018 record. The current level has gone past that assumption.

Danube level at Paks · measured and official forecast · 0cm now
Danube level (cm)
official forecast
earlier forecast (issued 3 days ahead)
The 2026 shutdown · Danube level and Paks output
closed period
live ·
Danube level (left, cm)
Paks output (right, MW)
Danube water temp (colour band)
2018 record
Back on the grid · the restart16days to full power
closed period
Danube level (left, cm)
Paks output (right, MW)
Danube water temp (colour band)
the level before the shutdown
How much does the plant warm the Danube?°C warmer
measured heat excess

The Danube's temperature is measured in several places. Paks, still upstream of the warm-water outfall, and at Dombori, 25 kilometres below the Paks gauge — the difference between them shows how much warmer the water flows on after the plant has used it for cooling. The relationship can be drawn at all because output this year covered the whole range: the record-low Danube pushed it from 2000 MW nominal down to 230 MW — three units stopped, the fourth ran at half steam — then it climbed back over three weeks. Per gigawatt the water warms by roughly °C.

Why does so much heat end up in the river? Because heat cannot be turned into electricity without loss: a steam cycle needs a cold side for the unused heat to go — at Paks that is the Danube. The units are roughly 33%-efficient, so only a third of the heat made in the reactor becomes electricity; the other two thirds flow away with the cooling water. That is why the plant puts roughly twice as much energy into the river as heat: at 2000 MW of electricity, close to 4 GW.

The technical term "Paks thermal plume" does not mean this average excess but the sharply bounded warm band within the cross-section: it runs along the right bank, near the outfall it can be as much as 8–10 °C hotter than the untouched part of the section, and it stays distinguishable all the way to Mohács.

The heat excess on the Danube
how much warmer the water is
0 °C+2 °C
detection limit ±0.7 °C

Drag the curve, or press play: the plume appears and fades with output.

The plant, in a nutshell
The same water goes round and round: heated from below, the steam spins the turbine, then condenses in the cold Danube and starts over. The cold side is not optional — without it the cycle would stop. The numbers, though, are Paks's own: a third of the heat becomes electricity, the rest warms the river.
Rock into the Danube · a bottom sill on the riverbedcm higher · estimate
announced12 Aug 2026first phase done29 Aug

The plant's cooling water is drawn from the Danube by the main cooling-water pump intakes — they sit at a fixed height, the river's level does not. That is exactly what caused the summer shutdown: the water dropped so low that the pumps had nothing left to draw.

Between Paks and Dunaszentbenedek, downstream of the plant — at river-kilometre 1526 of the Danube, below the mouth of the cold-water canal — a rock sill is being built on the riverbed. The first phase was completed by 29 August: 43 thousand cubic metres of rock, across the full width of the riverbed. The rest of the planned 145 thousand goes into reinforcing the bed below the sill, because the water, accelerated in the narrows, scoured out 8–13 metres. The sill does not block the river: the Danube keeps flowing, but the rock dams back the reach above it — the one the plant draws its water from.

How much does the sill raise the water?ESTIMATE · FROM MEASURED DATA
cm

This is how much higher the Danube stands at the Paks gauge than the Dombori gauge, below the sill, would warrant — daily mean. The solid line is the measured stage, the dashed one the computed stage without the sill.

still being built · phase 2
How is the number derived?Hide the derivation
Top: hourly stage at the Paks and Dombori gauges from 1 June to today, Dombori shifted back by 8 hours. Bottom: every low-water hour is a point, Dombori horizontally, Paks vertically. Hours before the sill sit on one curve; hours after it move above the curve — the distance is the effect of the sill.

Scheduled vs. actual grid load · 24 hours0MW below plan
0MW below schedule · past hour
Below schedule 0 / 0 quarter-hours That’s 0 GWh less than the schedule since midnight

The “schedule” is MAVIR’s own forecast, so the gap includes forecast error — on its own it does not prove deliberate saving, but it shows the direction well.

What the electricity came from · 24 hours

The layers add up to consumption: whatever is not generated at home is covered by imports.

Where is the power coming from? · 0 MW
Consumption, generation, cross-border flows, Paks output: MAVIR. Danube level, water temperature, discharge: vizugy.hu, Paks gauge. Unit statuses: MVM Paks Nuclear Power Plant announcements. Day-ahead price: energy-charts.info — data source Bundesnetzagentur | SMARD.de, CC BY 4.0, unmodified. Rain forecast: Open-Meteo, CC BY 4.0. Catchment boundaries: HydroSHEDS / HydroBASINS (WWF), CC BY 4.0. EUR/HUF: ECB reference rate. Frequency: Fraunhofer ISE, Freiburg.
ittadelej@holadelej.hu